Skip links

How Long Does It Take to Remodel a Bathroom?

Are you thinking of having your bathroom remodelled? If so, you may be wondering about the timeline of this home renovation endeavour. Weeks, months, or perhaps even years?

Before getting started, make sure that you already have an idea of the estimated time of completion. After all, the bathroom is an essential part of the household and plays a critical role in your daily routine. It is where you will go immediately after waking up – as well as right before heading to bed for a restful sleep.

With that being said, you would want to know how long your bathroom will be out of action so you and your family can prepare accordingly. And in this detailed article, we will take a closer look at the timeline associated with remodelling a bathroom.

How Long Does a Bathroom Remodel Take to Complete?

Under ideal conditions, a bathroom renovation will take around 23 days or at least 4 weeks to complete. But truth be told, this is an extremely ambitious time frame. After all, there are several factors to consider, including downtime and any setbacks that the workers will encounter along the way. Plus, the amount of labour done per day is seldom uniform, and some days will naturally be more productive than others.

With that being said, make sure to be realistic about your expectations. At the very least, you can anticipate the bathroom remodel to take twice as long to finish, which translates to anywhere between 8 and 9 weeks or even longer.

What Factors Affect the Timeline of Bathroom Renovation?

As previously mentioned, various factors can influence bathroom renovation time. This includes the extent of the project, the bathroom size, your choice of materials, and whether or not the remodel will be done by an expert. We run through them below.

1. Scope of the Bathroom Remodel Project

A bathroom remodel can either be a makeover or a full-scale renovation. If you are simply replacing old, damaged fixtures or improving the bathroom’s design elements, you may only need a few days to a week to finalize the project. But if you are planning to revamp your bathroom from scratch, the workers will definitely need more time to get things done. It can take anywhere from a few weeks to several months, depending on the extent of the remodel.

2. Size of the Bathroom

This requires no explanation. Of course, the larger the bathroom, the more time is needed to complete the renovation project. An outsized bathroom will most probably require more than 9 weeks for a full-scale remodel.

Related article: How Much Does It Cost to Remodel a Small Bathroom in Toronto?

3. Material of Choice

Your preferred materials can have a significant impact on the project timelines. Specifically, you will have to consider the availability, accessibility, and ease of installation of your preferred products.

Premium materials are most likely to be pre-order and can take weeks to arrive at your doorstep. They may also require special handling, packaging, and shipping, which can further extend the project duration. On the other hand, some products may be obtained at the local hardware store within a few hours.

Aside from the availability and accessibility, you will also need to think about the preparation and installation requirements. Some are more difficult to set up than others, thereby stretching the timeline even further. In line with this, opting for customized instead of pre-made furnishings – such as cabinets – can also prolong the remodel time frame.

4. DIY vs Professional Work

Will you be remodelling your bathroom or will professional workers be handling the job? If you want to go the do-it-yourself route, you can expect the bathroom renovation to take longer to finish. It is not merely because of the differences in skill and experience, but also because of the level of commitment involved.

If you are doing the renovation yourself, you will most likely just work on your bathroom whenever you are available, such as every weekend. In this case, it may take you months to progress on your to-do list, and years to completely finish the task at hand.

In contrast, hiring a bathroom renovation contractor or company can significantly speed things up. After all, they will work on your bathroom continuously – save for downtime and other interruptions. However, you will also have to consider if they offer full services (which means that they are in charge of the whole renovation process) or they are subcontracting electricians, plumbers, and other workers. If it is the latter, then the deadline can stretch further.

If you choose a reliable contractor, you don’t have to worry much about the schedule. After all, they will provide you with a detailed breakdown of the tasks, as well as a realistic target date of completion.

Related article: How to Choose the Best Bathroom Remodelling Contractor

time taking for remodel bathroom

What Is the Timetable for a Bathroom Renovation Project?

After familiarizing yourself with the most common factors that can delay your carefully planned renovation, the next step is to explore the specifics of the project itself. That is, we will talk about the tasks involved in a typical bathroom remodelling project – from start to finish. Refer to the timetable below for the approximate time of completion for each step.

Task Allotted Time
Demolition work 2 days
Rough carpentry work or framing 2 days
Plumbing work 1 to 2 days
Electrical work 1 to 2 days
Initial inspection 1 day
Insulation and drywall installation 3.5 days
Painting 1 day
Final inspection 1 day
Tiling 2 days
Flooring 2 days
Cabinetwork 1 day
Final touches 2 days
Miscellaneous 1.5 days
Estimated time of completion 21 to 23 days

Note: Keep in mind that this is only a sample timetable and task breakdown. Again, it all varies from one remodel project to another. Some may skip a couple of steps in this list, while others may require a few extra steps. The contractors may also spend less or more time per task. 

Related article: How Much Does It Cost to Remodel a Small Bathroom in Toronto?

A Realistic Timeline for Bathroom Renovation Projects

Many homeowners will have to remodel their bathrooms at one point or another – whether it is simply a minor makeover or a major overhaul, complete with stripping the room bare. Either way, you would want to know how long it will take for your newly revamped bathroom to become serviceable again.

On average, you need to set aside at least 9 weeks for the bathroom remodel. But depending on several factors, the renovation project can take anywhere between a few days to several months. You also have to accept that anything can throw off your well-thought-out schedule, including extra repairs, delayed deliveries, and many more.

Basically, you never know what is going to happen, so it is important to set aside some extra time to deal with contingencies. Also, never rush your contractors. The last thing you want is for them to compromise the quality of their work.

At the end of the day, the only way to know the reasonable time frame of completion is to consult with a capable bathroom remodelling contractor. After all, it varies immensely from one project to another.

Looking for a trusted company to turn your dream bathroom into a reality? Here at BR Bathroom Renovations Richmond Hill, we have got you covered. We work efficiently and are transparent with every detail of the project. More importantly, we will provide you with a realistic timeline so that you will have an idea of what to expect. Call us at (647) 834-8346 or fill out this contact form to schedule an appointment.

Leave a comment